Your Questions Answered
How did the B1122 Action Group respond to EDF's Stage 2 Consultation?
Our response document can be read or downloaded here. Will it really be as many as 900 additional trucks a day? All our statistics are taken from EDF's own figures in their Stage 2 response. The 900 does not include existing truck traffic, or Park & Ride buses. Won’t rail and sea transport cut this down? No. EDF’s estimates already assume that they will get all the extra rail and sea facilities that they want. If they don’t, even more will have to go on the road. We coped with Sizewell B - will it be any worse? Yes. Sizewell C will have two reactors, will be over twice the size of B, and will need over double the building materials and equipment. |
|